Infrastructure on Atatürk Street and Ahmet Tokuş Boulevard Is Being Upgraded in Alanya

Infrastructure on Atatürk Street and Ahmet Tokuş Boulevard in Alanya is being upgraded to meet the city’s needs for the next 50 years. The work is being carried out under the coordination of the municipality and covers water, gas, and telecommunications networks. According to Alanya Haber, the project is scheduled for completion on 30 April 2027.

The second phase of work on Ahmet Tokuş Boulevard began on 2 November 2026 near the Mola intersection, next to the Alanyaspor Store. The work has progressed toward the Yalı Taxi area; municipal services and staff from relevant organizations are working on site simultaneously. For residents and property owners, this means that several types of networks are being upgraded as part of one project.

ASAT, Alanya’s water utility, is replacing old drinking-water pipes, while gas company Enerya is installing gas infrastructure. Telecommunications organizations are upgrading the fiber-optic network. The coordinated work schedule is intended to reduce the likelihood of repeated excavations on the same streets in subsequent years.

On Ahmet Tokuş Boulevard, ASAT is laying O-PVC pipes with a diameter of 160 mm; pipes with diameters of 225 and 110 mm were also used in November 2025. ASAT construction site manager Eray Aytaç said the existing water networks consist of worn-out pipes that are 40–50 years old. Once the upgrade is complete, the aim is to provide homes with a more stable water pressure.

Enerya plans to lay about 3 km of gas pipeline on Ahmet Tokuş Boulevard and leave branches for subscribers, hotels, and businesses. The new section is to be connected to the Çıplaklı gas line. According to Enerya construction site manager Muhammet Ali Topuz, this will allow the new network to be integrated with sections already built.

To connect to the new section, Enerya is using a network that includes 7 900 m of main pipes and 108 service lines laid in 2025. The company plans to supply gas this year; Alanya Haber’s publication of 13 November 2026 does not specify a separate launch date. Branches are planned for private subscribers, hotels, and businesses along the route.

The project also includes upgrades to the fiber-optic network and surveillance camera infrastructure. According to Alanya Municipality information technology department employee Ercan Güven, cameras in parks are planned to be connected to the central system, and their number will be increased. The work affects, among other areas, busy streets and avenues.

Before the upgrade began, no comprehensive work had been carried out on Atatürk Street and Ahmet Tokuş Boulevard since 1996. The municipality plans to remove the existing paving-stone surface and lay hot asphalt. Once the underground work is complete, asphalting and improvements to the sidewalks are planned.

According to Alanya Haber, during the first phase ASAT carried out about 1 400 m of excavation between the Atatürk monument and the Yalı Taxi area; pipe laying and connections to subscribers are ongoing. Work on the fiber-optic network in this section has been completed. The overall project deadline, including subsequent upgrades to the road surface and sidewalks, is 30 April 2027.

Back to News
We will help you sell your property quickly and profitably
We will quickly and most importantly put your property up for sale at a profit. Guarantee and transparency of transaction support.
Stay Property Projects
We have been engaged in construction for more than 20 years. Leave a request and we will send you a price list.
Our YouTube channel
Life in Alanya, real estate review, legislative news and much more...
More details